Customer: North American Mineral Producer
General Contractor: Galyon Brothers Construction
Structural Engineer: Engineering Consultants
Installed Cost: $2 million
Century-old plant was fully operational during design, demolition and installation of new structural steel.,
This $2-million capital project renovated the century-old vacuum building of the plant’s vacuum pan evaporation process. The AIG team was responsible for several phases of the project:
- Structural engineering design of shoring to support wooden structure during demolition.
- Mechanical engineering support.
- Bid package development.
- Full-time, on-site safety coordination.